3 persons can repair a road in 25 days, working 7 hours a day. In how many days will 11 persons, working 13 hours a day, complete the work
Solution Breakdown:
11×13×x=3×7×25 = 3.67
Question 2Hard
35 persons can repair a road in 27 days, working 13 hours a day. In how many days will 29 persons, working 9 hours a day, complete the work
Solution Breakdown:
29×9×x=35×13×27 = 47.07
Question 3Hard
41 persons can repair a road in 21 days, working 3 hours a day. In how many days will 31 persons, working 1 hours a day, complete the work
Solution Breakdown:
31×1×x=41×3×21 = 83.32
Question 4Hard
21 persons can repair a road in 25 days, working 13 hours a day. In how many days will 21 persons, working 13 hours a day, complete the work
Solution Breakdown:
21×13×x=21×13×25 = 25
Question 5Hard
39 persons can repair a road in 23 days, working 5 hours a day. In how many days will 1 persons, working 5 hours a day, complete the work
Solution Breakdown:
1×5×x=39×5×23 = 897
Question 6Hard
31 persons can repair a road in 11 days, working 15 hours a day. In how many days will 29 persons, working 15 hours a day, complete the work
Solution Breakdown:
29×15×x=31×15×11 = 11.76
Question 7Hard
47 persons can repair a road in 25 days, working 13 hours a day. In how many days will 23 persons, working 7 hours a day, complete the work
Solution Breakdown:
23×7×x=47×13×25 = 94.88
Question 8Hard
7 men and 3 women complete the work together in 10 days. 8 men and 2 women complete the same work In 8 days. How much work can be done by 10 men in one day?
Solution Breakdown:
No Details
Question 9Hard
Badki can bake 45 cakes in 9 hours, Badki and Chutki together can bake 80 cakes in 10 hours. How many cakes Chutki can bake in 40 hours?
Solution Breakdown:
No Details
Question 10Medium
A can do a work in 20 days and B in 50 days. If they work on it together for 5 days, then what fraction of work is left?