If 34 men completed 2/5th of a work in 8 days working 9 hours a day. How many more man should be engaged to finish the rest of the work in 6 days working 9 hours a day?


Detailed Solution:

From the above formula i.e (m1*t1/w1) = (m2*t2/w2) so, (34*8*9/(2/5)) = (x*6*9/(3/5)) so, x = 136 men number of men to be added to finish the work = 136-34 = 102 men