If 34 men completed 2/5th of a work in 8 days working 9 hours a day. How many more man should be engaged to finish the rest of the work in 6 days working 9 hours a day?
A) 89
B) 98
C) 102
D) 142
Explanation:
From the above formula i.e (m1*t1/w1) = (m2*t2/w2)